PSU Design Standards Revisions

TitleEffective DateDescription
Section 26 00 00 ElectricalJun 06, 2017 10:55 AM
 An update to the University’s lighting standards throughout division 26; to accomplish needed change and revision. Section 26 09 23 Lighting Control Devices and Systems, 26 51 00 Interior Lighting, 26 52 00 Emergency Lighting

Section was updated primarily for the following reasons:

    1)  An update to the University's lighting standards throughout Division 26; to accomplish needed change and revision.


Section 01 35 20 Safety RequirementsMay 22, 2017 11:45 AM
 To add sub section .03 Prevention through Design Standards

Section was updated primarily for the following reasons:

   1)Too add sub section .03 Protection through Design Standards

Section 23 21 13 Hydronic Piping GuidespecMar 22, 2017 07:05 AM
 Complete replacement of existing word document specification in table

Section was updated primarily for the following reasons:

1) To replace existing document specification in table

Section 33 40 00 Stormwater DrainageMar 16, 2017 02:10 PM
 Stormwater section major delete and replace

Section was updated primarily for the following reasons:

1.) Delete current section and its entirely and replace with new section

Section 23 25 00 HVAC Water Treatment-commonwealth -PDFMar 13, 2017 02:40 PM
 Water treatment Commonwealth

Section was updated primarily for the following reasons:

1). add this section for Commonwealth

Section 23 21 13 D02 pdfMar 13, 2017 02:35 PM
 Hydronic Plant Piping Schematic D2

Section was updated primarily for the following reasons:

1.) to replace current schematic with new one.

Section 23 21 13D01pdfMar 13, 2017 02:30 PM
 Hydronic Plant Piping Schematic

Section was updated primarily for the following reasons:

1.) to replace current schematic and replace with new.

Section 23 25 00 HVAC Water Treatment-commonwealth -word docMar 13, 2017 08:55 AM

HVAC Water Treatment for Commonwealth

Section 23 25 00 HVAC Water TreatmentMar 09, 2017 08:20 AM
 Section was updated to meet Project-specific requirements.

Section was updated for the following reasons:

1)  To meet Project-specific requirements.

Section 26 00 00 LightingNov 03, 2016 11:03 AM
 Update lighting standards throughout division 26

Section was updated primarily for the following reasons:

1) An update to the University's lighting standards throughout division 26; to accomplish needed change and revision.

Section 25 55 00Oct 26, 2016 03:03 PM
 Replaced section 25 55 00 dated Sept. 2016 with revised section 25 55 00 dated Oct. 2016

Section was updated for the following reason:

 1) Replaced section 25 55 00 dated Sept. 2016 with revised section 25 55 00 dated Oct. 2016.

Section 23 82 00 Convection Heating and Cooling UnitsOct 05, 2016 11:10 AM
 Modified subsections .01 and .02 regarding coil selection criteria, including the intent to support the future use of 140 degree water.

Section was updated primarily for the following reasons:

1)    To remove inaccurate/outdated selection criteria and replace with intent for high-performance design selections. 

2)    To include requirements to select heating coils to support the future use of 140 degree supply water temp from alternative low temperature heat sources in the future. 

3)    To require stainless steel coil casings on applications that will condense moisture

Section 25 55 00Sep 22, 2016 02:00 PM
 Replaced section 25 55 00 dated NOV2015 in its entirety with new section 25 55 00 dated SEPT2016

 Section was updated for the following reason:

 1) Replaced section 25 55 00 dated NOV2015 in its entirety with new section 25 55 00 dated SEPT2016.

Section 01 35 20 Safety Requirements

Access Ladders PDF

Sep 09, 2016 11:50 AM
 To revise safety requirements

Section was updated for the following reason:

 1) To revise Section on Safety Requirements

Section 26 50 00 LightingJul 19, 2016 09:22 AM
 A University lighting matrix was added to the standard for clarity.

Section was updated primarily for the following reasons:

1) A University lighting matrix was added to the standard for clarity.

Section 26 36 00 Transfer SwitchesJun 17, 2016 08:40 AM
 Deleted old section and replaced with new section, which includes a new guide specification section and new additional data sheet.

Section was updated primarily for the following reasons:

    1)  Deleted old section and replaced with new section, which includes a new guide specification section and new additional datasheet.

Section 26 22 00 Low-voltage TransformersJun 16, 2016 11:10 AM
 Deleted old section and replaced with new section, which includes a new guide specification section and new additional datasheet.

Section was updated primarily for the following reasons:

     1)  Deleted old section and replaced with new section, which includes a new guide specification section and new additional datasheet.

Section 26 24 16 PanelboardsJun 16, 2016 11:10 AM
 Deleted old section and replaced with new section, which includes a new guide specification section and new additional datasheet.

Section was updated primarily for the following reasons:

   1)  Deleted old section and replaced with new section, which includes a new guide specification section and new additional datasheet.

Section 26 32 13 Engine GeneratorsJun 16, 2016 11:05 AM
 Deleted old section and replaced with new section, which includes a new guide specification section and new additional datasheet.

Section was updated primarily for the following reasons:

    1) Deleted old section and replaced with new section, which includes a new guide specification section and new additional datasheet.

 

 

Section 26 24 13 SwitchboardsJun 14, 2016 02:30 PM
 Delete old section and replace with new section

Section was updated primarily for the following reasons:

     1) Deleted old section and replaced with new section, which includes a new guide specification and new additional datasheet.

Section 26 05 53 Identificaiton for Electrical SystemsJun 08, 2016 10:35 AM
 Delete and replace section

Section was updated primarily for the following reasons:

     1)  Deleted old section and replaced with new section, which includes a new guide specification section.

Section 26 05 73 Power Systems StudiesJun 08, 2016 09:15 AM
 Deleted old section and replaced with new section, which includes a new guide specification section and sample standard arc flash labels.

Section was updated primarily for the following reasons:

      1) Deleted old section and replaced with new section, which includes a new guide specification section and sample standard arc flash labels.

Section 26 05 26 GroundingJun 02, 2016 02:00 PM
 Section deletion and replacement

Section was updated primarily for the following reasons:

     1) Deleted old section and replaced with new section, which includes a new guide specification section and updated grounding details.

Section 26 00 01 Owner General Requirements

Data Sheet Completion Instructions

Jun 02, 2016 09:30 AM
 rev to part E

Section was updated primarily for the following reasons:

     1) Added data sheet instructions in preparation for addition of new data sheets throughout standards.

28 00 00 Electronic Safety and SecurityMay 19, 2016 01:55 PM
 Update Fire Alarm Standards

Section was updated primarily for the following reason:

1) To update Fire Alarm Standards

22 31 00 Domestic Water SoftenersMay 19, 2016 11:05 AM
 Revisions to the domestic water softener section to remove ion exchange softeners.

Section was updated primarily for the following reason:

1) To revise the domestic water softener section to remove ion exchange softeners.

01 05 05 Space PlanningMay 17, 2016 02:10 PM
 .07 Addition of Lactating Rooms to PSU Design & Construction Standards

Section was updated primarily for the following reason:

1) To add the addition of Lactating Rooms to PSU Design & Construction Standards

01 05 05 Space PlanningMay 17, 2016 01:55 PM
 To revise Section .05 Unisex Toilet Rooms

Section was updated primarily for the following reason:

1) To revise Section .05 Unisex Toilet Rooms

01 40 00 Quality RequirementsApr 25, 2016 10:46 AM
 Revised Environmental Compliance Checklist 4-4-16

Section was updated primarily for the following reason:

1) To revise Environmental Compliance Checklist

09 68 10 Carpet TileApr 25, 2016 10:15 AM
 Revisions to 096810 Carpet Tile as a result of the most recent University Sustainable Carpet Committee assessment process.

Section was updated primarily for the following reasons:

     1)  To revise section 096810 Carpet Tile as a result of the most recent University Sustainable Carpet Committee assessment process.

32 00 00 Exterior ImprovementsApr 13, 2016 02:55 PM
 32 90 00.02 Planting Revisions

Section was updated primarily for the following reasons:

1) To revise Lawn and Grasses Construction Standard in Division 32   32 90 00.02

01 40 00 Quality RequirementsJan 12, 2016 09:25 AM
 Revised Environmental Compliance Checklist

Section was updated primarily for the following reasons:

1)  To revise Environmental Compliance Checklist

23 00 10 Subsection 12Dec 16, 2015 09:34 AM
 Laboratory Ventilation Systems - Replace entire subsection

Section was updated primarily for the following reasons:

 1)      To make various additions and revisions throughout the entire

 section including, but not limited to, PSU Environmental Health and Safety  Requirements, Laboratory Fume Hoods and Other Containment Devices, Anatomy  Laboratory and Specialty Containment Exhaust Systems

25 00 00Dec 02, 2015 10:15 AM
 25 55 00 BAS Guide Spec Update -November 2015 version

 Section was updated primarily for the following reasons:

1. To add requirements for software license(s)

2.  To add requirements for "Construction Server"

23 00 10 Subsection 12Nov 16, 2015 11:25 AM
 Lab Vent Systems - EHS Interim Guidance

Section was updated primarily for the following reasons:

 1)      To remove prior guidance relative to EH&S and establish interim communication plan until updated requirements are published.

25 00 00Nov 02, 2015 02:10 PM
 25 55 00 BAS Guide Spec Update - October 2015 version

Section was updated primarily for the following reasons:

  1. Replaced old document name "Building Automation Systems (BAS)" and June 2014 version date with new document name "25 55 00 BAS GuideSpec"and October 2015 version date.
  2. Update summary is included in front end of document.
08 70 00Oct 27, 2015 01:45 PM

Updated door hardware

Section 07 00 00Oct 07, 2015 04:10 PM
 Section was updated to reflect changes in roof construction.

Section was updated to reflect changes in required slope for new versus existing roofs; removing the prohibition on APP systems; changing the requirements of roof insulation systems; increasing the height of required flashing; and adding drain sumps.

Section 23 21 13Oct 07, 2015 10:10 AM
 Section was updated to reflect prohibition on air pressure testing in hydronic piping systems.

Section was updated to reflect prohibition on air pressure testing in hydronic piping systems. Superceded Section 23 21 13 Hydronic Piping

Section 08 00 00Jul 14, 2015 10:00 AM
 Section was updated primarily for the following reasons:

1) To rename main heading of Division to match current industry practice
2) To consolidate requirements associated with windows (insulated glass units)
Superceded Section 08 00 00 Openings- consolidate window requirements

Section 01 81 13Jul 13, 2015 09:35 AM
  Added alternate bid requirements for Energy Conservation options.

Section was modified primarily for the following reasons:

1.    To define requirements for alternate bids for Energy Conservation options to provide the opportunity for the Owner to select and fund additional energy optimization features beyond the minimum project scope.

Section 32 90 00Jul 10, 2015 10:20 AM
 Modified subsections .02 and .03

Section was updated primarily for the following reasons:

1) To revise requirements for Planting Seasons

2) To revise maintenance requirements of trees and shrubs

3) To add/modify other miscellaneous requirements and corrections


Section 14 20 00Jul 01, 2015 02:50 PM
 Updated entire section on Elevators

Section was updated primarily for the following reasons

1)    To revise criteria for type of elevator to be used based on the number of floors it serves 

2)    To update various references to construction codes and industry standards for work associated with elevators 

3)    To revise the lists of manufacturers for elevators, controllers, and miscellaneous accessories 

4)    To update requirements for the Remote Monitoring System 

5)    To change elevator car lighting from fluorescent to LED 

6)    To revise/clarify other miscellaneous requirements


Section 25 00 00Apr 30, 2015 03:09 PM
 Updated document table in section 25 00 00. Remainder of section is unchanged.

Section was updated primarily for the following reasons:

  1. This is an upgrade to the existing process, whereby a member of the Facility Automation Services department controls and assigns the BACnet and network numbers.


Section 01 81 13Apr 03, 2015 12:10 PM
 Deleted .01 Owner General Requirements and Design Intent and .02 LEED Certification Requirements and replaced with new text.

Section was updated primarily for the following reasons:

  1. To remove miscellaneous general design intent language that is now covered in a more specific detail of the cited combination of High Performance Building Design Standards.
  2. To clarify the specific versions of high-performance energy standards of ASHRAE 90.1 and 189.1 presently adopted by OPP.
  3. To remove the language in the "Advanced Energy Performance Target" that has become outdated due to incremental advances in the cited Energy Performance standards.  For projects that are not LEED, complying with the cited High-Performance Building Design Standards will achieve the intent.  For LEED projects, any such "Energy Performance Target" for the credit to "Optimize Energy Performance" shall be defined in the PSU LEED policy.
  4. To emphasize the Building Envelope Energy Component requirements and associated compliance documentation.
  5. To revise the correct title and hyperlink to the "PSU LEED Policy" document and to provide interim direction during migration period between LEED versions.


Section 23 00 01Mar 20, 2015 01:45 PM
 Added link to 01 00 00 General Requirements

Section was updated primarily for the following reasons:

  1. To remove outdated reference and replace with more comprehensive requirements throughout Division 1.


Section 01 50 00Mar 17, 2015 02:22 PM
 Added new subsection 01 56 16 to section 01 50 00

Section was added primarily for the following reasons:

  1. To add new section to define requirements for specifying dust barriers and other construction IAQ control methods to effectively isolate construction work areas from the surrounding occupied areas.
  2. To include definitions and roles of supporting parties.
Section 26 36 00Mar 16, 2015 09:10 AM
 Modified section 26 36 00

Section was updated primarily for the following reasons:

  1. Changed to eliminate a confusion issue when specifying equipment during design.


Division 26 00 00Feb 20, 2015 03:07 PM
 Revised various sections in Division 26

Sections were updated primarily for the following reasons:

26 00 01 - Section D was added to add to address the new Electrical Load Determination Form and to provide a hyperlink to the document.  Original sections D & E were relabeled due to the additional section D.  Section G was added to provide clarity to the designer and to ensure Engineering Services, Electrical Department is aware of any exceptions taken.

26 00 02.10 - Revision to section A, Motors, was added to give direction to the designer when and where to utilize VFD cables.

26 05 10.01 - Added sections G & H.  G was added to outline the specifications for VFD rate cable and to provide directive to the designer.  H was added to provide specifications for compression lugs.

26 05 26.01 - Added sections J, K & L.  J was added to clarify the use of a specific type of compression lug. K was added to clarify that PCV is preferred but RMC can be used if certain guidelines are followed.  L was added to hyperlink to PSU'ss typical design drawings for reference.

26 05 43.01 - Section F was updated to call out the use of detectable warning tape and to outline the specifications for the warning tape.  Section G was added to add a hyperlink to the typical CADD details for PSU Ductbanks.

26 05 43.02 - Section H was updated to add hyperlinks to PSU typical CADD details.

26 05 53.01 - Section J was added to address new labeling requirements for electrical service equipment that feeds CRITICAL research equipment.

26 20 00.01 - Number 3 was updated to change how the drawings are stored and what are they stored in.  This was done to make it easier to see if the drawings are in the document tube and to make it easier to get the drawings out of the document tube.

26 23 00.02 - A new section was added to address new guide specifications; the table contains a hyperlink to the OPP Low-Voltage Switchgear Guide Specification.  The guide specification was added as an easy reference for the Design Professional.

26 36 00.01 - Section C was updated to provide the Design Professionals with a more comprehensive list of options that will be required on all transfer switches.

00 51 00 - Added a row to the table to address the new hyperlink for the new load determination form.

26 20 00.01 - Section was updated so that designers know to confirm with Engineering Services whether ARM system is required.

26 32 13 - Section was updated to cover CCS monitoring of generators since it was deleted from the BAS and needs to be addressed.

26 00 01 - Section was updated to address BAS issues.

26 50 00 - Section was updated to add reference to Elevator Service section that notes minimum illumination levels and to revise general lighting source to LED.

26 56 00 - Exterior Lighting section updated to require the 10,000 lumen Poulsen Lipp LED luminaire to PSU UP campus walkways.

Section 26 36 00Feb 06, 2015 10:55 AM
 Modified Section 26 36 00 Transfer Switches

Section was updated primarily for the following reasons:

  1. Changed section to avoid confusion with selection transfer switch options.
Section 23 21 23Jan 16, 2015 10:58 AM
 Modified subsection .03 in Section 23 21 23

Section was updated primarily for the following reasons:

  1. Edit Shutoff Valve requirements to cross reference where defined elsewhere in the OPP Standards to avoid duplication/conflicting guidance
  2. Clarify pump discharge check valve requirements
  3. Eliminate requirement for flow measurement station at each pump
  4. Revise requirements for flexible pipe connectors to use flexible metal type on systems with operating temperatures 105°F and greater
Section 23 25 00Oct 24, 2014 02:36 PM
 Modified Section 23 25 00 HVAC Water Treatment to include a new guide specification.

Section was updated primarily for the following reasons:

To add the guide specifications for closed systems.

To revise the portions of the standard associated with closed system to conform to the guide specifications.

Section 33 10 00Sep 19, 2014 02:17 PM
 Replaced Section 33 10 00 in its entirety

Section was updated primarily for the following reasons:

  1. To modify and expand some technical content requirements, including but not limited to, University Water Service and Water Line Extension Plan Approval Requirements, materials of construction, and changes in manufacturers' names.
  2. To reorganize the section into main parts as follows - General, System Requirements, Execution and Guideline Details.  Then System Requirements is organized starting with distribution and ending with building service entrances.
  3. Updated old drawings and added new drawings, each available in PDF or ACAD DWG electronic format.
Section 26 29 23Aug 27, 2014 01:00 PM
 Replaced OPP VFD GuideSpec document

Section was updated primarily for the following reasons:

  1. Revised VFD cable and cable installation requirements.
  2. Revised and replaced all occurrences of VFC to VFD throughout document.
Section 25 90 00Jul 29, 2014 12:42 PM
 Removed guide sequences of operation and replaced with guide sequences of operation

Section was updated primarily for the following reasons:

  1. To remove guide sequences of operation from the website because they are subject to frequent modifications and thus are impractical to keep updated on the website.
  2. To require that the Designer and the Control System Contractor always contact OPP FAS for the most current versions available for each project.
Section 25 90 00 (no link)Jul 29, 2014 12:25 PM
 Removed guide sequences table and replaced it with guide sequences of operation

Section was updated primarily for the following reasons:

  1. To remove guide sequences of operation from the website because they are subject to frequent modifications and thus are impractical to keep updated on the website.
  2. To require that the Designer and the Control System Contractor always contact OPP FAS for the most current versions available for each project.
Section 25 00 00Jul 15, 2014 09:48 AM
 Replaced updated Building Automation Systems (BAS) document

Section was updated primarily for the following reasons:

  1. Disallowed the use of Application Specific Controllers.
  2. Replaced Insight software (and misuse of Apogee term) with Desigo software.
  3. Clarified the intent of what stand alone at the terminal controller means.
  4. Clarified the intent of controlling only one major system from a single controller and using only one controller to process the entire program.
  5. Added an airflow trend COV increment.
  6. Replaced the Siemens System Architecture diagram.
Section 25 90 00Mar 18, 2014 03:53 PM
 Replaced the document for "Air terminal Units - Single Duct Variable Air Volume with Hot Water Reheat & Permiter Heating"

Section was updated primarily for the following reasons:

  1. Remove unneeded references to Division 26.
Section 01 41 00Mar 06, 2014 11:36 AM
 Updated Environmental regulatory Compliance Checklist and Addendum documents

Section was updated primarily for the following reasons:

  1. Include new asbestos containing material information.
Section 23 21 16Mar 03, 2014 01:53 PM
 Deleted subsection .05 Hydronic Specialties. Added section 23 21 16 in its entirety.

Section was updated primarily for the following reasons:

  1. To create distinct section to follow industry standard section number and to correlate with new guide specification section.
  2. To reorganize information more appropriately into Standards (to convey design intent) and Guide Specifications and Details (to be edited and included in Contract Documents) for clearer and more user-friendly and effective implementation between design and construction phases.
Section 26 50 00Feb 20, 2014 11:56 AM
 Modified subsection .01 - Lighting Design

Section was updated primarily for the following reasons:

  1. Add reference to Elevator Service section that notes minimum illumination levels.
  2. Revise general lighting source to LED.
Section 25 90 00Feb 12, 2014 02:04 PM
 Updated the EUMS document

Section was updated primarily for the following reasons:

  1. The EUMS has been greatly expanded and the sequence needed a major rewrite.
Section 22 11 00Dec 06, 2013 03:31 PM
 Deleted some text in subsection .01 of Section 22 11 00

Section was updated primarily for the following reasons:

  1. Information is incorrect in content and/or should not be in this section for regular plumbing water distribution.  Will be corrected in other revisions to follow.
Section 01 41 00Nov 14, 2013 10:03 AM
 Modified section 01 41 00 to include Environmental Compliance Checklist

Section was modified primarily for the following reasons:

  1. To clarify utility connection application requirements.
  2. To include the Environmental Compliance Checklist requirements.
Section 09 68 10Sep 18, 2013 11:26 AM
 Modified section 09 68 10

Section was updated primarily for the following reason:

  1. Clarify that broadloom carpet is NOT permitted.
  2. Add manufacturer website information.
Section 26 05 26Sep 16, 2013 02:24 PM
 Reworded subsection .01 General in Section 26 05 26 to include 2-hold lug requirement.

Section was updated primarily for the following reasons:

  1. Clarify that a 2-hold lug is required for all ground bus installations.
Section 23 05 01Jul 03, 2013 09:16 AM
 Modify subsection .02.A.4 in Section 23 05 01. Remainder of section is unchanged.

Section was updated primarily for the following reasons:

To modify general valve requirements for pipe insulation coordination to add insulated tee-handles for ball valves and preformed insulation kit covers for balancing valves.

Section 23 31 00Jun 25, 2013 02:49 PM
 Modified subsection .01 in Section 23 31 00. Remainder of section is unchanged.

Section was updated primarily for the following reasons:

  1. To prohibit the use of cloth-backed, rubber adhesive tape (commonly referred to as "duct tape") as a duct sealant.
  2. To prohibit the use of fibrous/fiberglass duct liner and to define product requirements for option to use flexible elastomeric sheets when needed for acoustic reasons.
Section 23 00 01Jun 20, 2013 11:50 AM
 Modified subsection .01, paragraph 5 in section 23 00 01. Remainder of section is unchanged.

Section was updated primarily for the following reasons:

  1. To add requirements that for areas with special pressure relationship requirements that must be properly controlled, the Design Professionals shall include plans in the construction set of drawings showing simplified pressure relationships and tabular summaries of overall air balance for each pressure controlled space and summaries of system airflows.
Section 23 00 10Jun 19, 2013 02:19 PM
 Added new subsection .12 in its entirety in Section 23 00 10

Section was updated primarily for the following reasons:

  1. Add new subsection defining OPP Laboratory Ventilation System requirements.
Section 23 07 00Jun 19, 2013 01:50 PM
 Deleted the current section and replaced it in its entirety

Section was updated primarily for the following reasons:

  1. To require use of most stringent minimum insulation R-value requirements in current codes and high-performance building standards in lieu of superseded ASHRAE 90.1 - 1999 reference.
  2. To require Corrosion Under Insulation Protection - coating ferrous piping under insulation.
  3. To add cross reference to HVAC duct section to be consistent on fiberglass duct liner policy.
  4. To coordinate optional additional insulation thickness on factory insulated packaged equipment to meet associated system insulation thickness.
  5. Other miscellaneous insulation revisions.
  6. To reorganize section into parts for General Owner, Product, and Execution requirements.
Section 08 00 00May 17, 2013 08:49 AM
 added specific requirements for thermally broken frames and edge spacers

Section was updated primarily for the following reasons:

  1. To add specific requirements for thermally broken frames and edge spacers between panes.
  2. To add certified performance by NFRC.
Section 23 41 00May 16, 2013 05:58 PM
 Added new text to 23 41 00

Section was updated primarily for the following reasons:

  1. change from old, outdated 30% efficiency rating to the MERV 8 called for by ASHRAE 189.1 High Performance Standard
  2. call for selecting more standardized filter and housing sizes to reduce maintenance costs
  3. call for sealing to prevent bypass pathways (per ASHRAE 189.1)
  4. prohibition of pre-filters with cardboard type frames in airstreams having characteristics that can cause the filter assembly to prematurely collapse
  5. add other general guidelines
Section 25 90 00May 16, 2013 04:51 PM
 Updated the table with a new document

Section was updated primarily for the following reasons:

  1. To emphasize the requirement for design professionals to define all airflow setpoints by moving it to the Notes at the beginning.
  2. To revise the reheat valve, damper and finned tube sequences to improve the stability and reliability of the control operations.
  3. To add chemical treatment subroutines.
  4. To redefine airflow and zone hot water requests.
  5. To redefine some alarming and alarm notification classes.
  6. To fix some formatting problems.
Section 01 78 46Mar 08, 2013 09:48 AM
 Added new subsection "01 78 46 Attic Stock" under section 01 70 00

Section was added primarily for the following reasons:

  1. To add new section to define requirements for coordinating and sepcifying attic stock.
Section 23 34 00Feb 27, 2013 12:14 PM
 Replaced Section 23 34 00 in it's entirety.

Section was updated primarily for the following reasons:

  1. To develop and document General Owner Requirements in order to define basic design intent and selection criteria.
    1. Goal – to provide guidelines to promote and achieve Efficiency and Reliability throughout entire operating range.
    2. To add requirements for limiting allowable fan power which include minimizing system air pressure drops and optimizing selection of efficient fans.
  2. To update the Equipment Requirements for fans, motor and drive components, and accessories to achieve better and more serviceable fan systems.
  3. To develop and document the Execution (Installation, Operation and Start-up/Commissioning) requirements.
    1. Goal – to achieve better installations, better operating efficiency and longer life from fan systems.
    2. Note the following special points:
      1. Minimize fan System Effects:  Avoid poor fan inlet and outlet conditions. Comply with manufacturer’s installation guidelines.

 

Section 26 22 00Dec 10, 2012 11:15 AM
 Updated Section 26 22 00

Section was updated primarily for the following reasons:

  1. It has been derermined through life cycle cost calculations on multiple projects that high effeciency transformers are a good investment with relatively short payback especially compared to the average life of the equipment.
  2. All major manufacturers offer competing products to make the bidding competitive.
Section 26 56 00Nov 28, 2012 08:29 AM
 Added new test related to pole manufacturers and sensor control of luminaires

Section was updated primarily for the following reasons:

  1. Updated acceptable pole manufacturers based upon feedback from the UP crew that maintains campus exterior luminaires.
  2. Added requirement to consider sensor control of parking lot luminaires.
Section 26 09 00Nov 27, 2012 02:19 PM
 Updated requirements for occupancy sensor controls.

Section was updated primarily for the following reasons:

  1. Update of occupancy sensor control requirements to reflect current PSU control strategies.
  2. Added list of acceptable controls manufacturers and new technologies.
Section 26 53 00Nov 26, 2012 12:14 PM
 Added clarification regarding acceptance of red LED exit signs.

Section was updated primarily for the following reasons:

Clarification that red LED exit signs are acceptable for small renovations projects to match existing.

Section 26 00 01Oct 29, 2012 10:01 AM
 Modified .10 Scope to add new paragraph "h" under Support Circuitry.

Section was updated primarily for the following reasons:

  1. Pennsylvania elevator code requires that the illumination level on the lobby side of every landing be a minimum of 10 fc at all times.  This criteria was not clear in the design standards and has been a point of problems during the inspection of elevators in recent construction.
Section 26 05 43Oct 29, 2012 08:50 AM
 Added paragraph to .01 Underground Ducts and Raceways for Electrical Systems

Section was updated primarily for the following reasons:

  1. There was a formatting error, a new paragraph D was created to separate information regarding steel reinforcing and the installation of a concrete base for the ductbank.  The concrete base is always required while the reinforcing is only necessary for vehicle traffic ares.
Section 26 52 00Oct 29, 2012 08:35 AM
 Added additional paragraph in .01 General (26 52 00 Emergency Lighting)

Section was updated primarily for the following reasons:

  1. To include the requirements of the Pennsylvania Elevator Code to the consultants to try and avoid issues during state Inspections.
Section 26 50 00Oct 26, 2012 12:37 PM
 Added subheading .01 in 26 50 00. Reworded .01 and .02, and added subheading .08 in 26 51 11. Remainder of section is unchanged.

Section was updated primarily for the following reasons:

    1. Update based upon the reduction of LED luminaire pricing to consider this source for more general applications.
    2. Clarify the type of T8 lamps to specify based upon Energy Conservation Measures instituted.
    3. Add requirement for some spare parts, especially to deal with the increased use of LED and the fact that these sources and drivers are sometimes difficult to match only 1 year after substantial completion.
Section 33 62 00Oct 11, 2012 09:48 AM
 Replaced documents with updated details and sequences

Section was updated primarily for the following reasons:

  1. Update details and sequences of operation to represent current operational requirements.
Section 23 21 13Sep 20, 2012 03:30 PM
 Deleted subsection .01 and .02 and replaced with new .01 to .04 in their entirety. Relocate text from existing subsection .03 to new .05 and delete remaining existing subsections.

Section was updated primarily for the following reasons:

  1. To add guidelines and requirements for the basic design of hydronic piping.
  2. To add 23 21 13 Hydronic Piping Guide Specification Section.
  3. To edit and reorganize to minimize duplications and cross references with other related sections 23 21 00 and new guide specification.
  4. To add new Hydronic Plant Piping Detail #2 for separate air and dirt eliminators.
Section 23 05 01Aug 31, 2012 03:38 PM
 Added a link to 23 21 00 Hydronic Piping and Pumps in subsection .02 B

Section was updated primarily for the following reasons:

This list of locations for shutoff valves is being moved to the Hydronic System general design requirements.

Section 23 22 00Aug 17, 2012 12:57 PM
 Added Subsection .04 to Section 23 22 00

Section was updated primarily for the following reasons:

  1. To relocate this reference to steam boiler blowdown from previous Section 23 21 13 Hydronic Piping into the more applicable steam piping section.
Section 23 21 00Aug 16, 2012 04:10 PM
 Removed existing subsection .01 and replaced with new text. Added new text in subsections .03, .04, .05, and .06. Subsection .02 unchanged.

Section was updated primarily for the following reasons:

  1. To remove reference to Bell and Gossett guidelines with respect to air separators.  Air eliminators are now covered in greater detail in Hydronic Specialties.
  2. To add guidelines and requirements for the basic design of hydronic systems.
  3. To remove reference to “ethylene” glycol since other types might be used.
  4. To remove reference to flow measuring devices, which are covered more in depth in subsection .02 of section 23 2100.
  5. To consolidate and relocate various references from Section 23 21 13 Hydronic Piping into this more general design guideline for Hydronic Systems.
Section 09 60 00Aug 02, 2012 04:06 PM
 Added Section 09 60 00 to Division 09.

Section was updated primarily for the following reasons:

  1. Add carpet tile requirements to standards.
Section 25 00 00 (no linked file)Jul 24, 2012 03:48 PM
 Replaced link to revised document "Building Automation Systems (BAS)"

Section was updated primarily for the following reasons:

  1. Corrected typos and minor edits.
  2. Added Index Title and Repaired Index.
  3. Clarified role of CSC for third party interfaces.
  4. Added Delta Controls and Siemens Apogee to Automated Logic as approved bidders and products providers.
  5. Removed Johnson Controls, Inc. from the approved bidders and products providers.
  6. Updated Codes and References section.
  7. Modified control power and UPS requirements.
  8. Clarified BAS Intent Meeting requirements.
  9. Updated BAS Shop Drawing requirements.
  10. Updated Global Building Controller and Application Controller requirements.
  11. Removed requirement for laptop computers.
  12. Added segmented V-ball control valves.
  13. Updated licensing requirements.
  14. Added language allowing line code programming.
  15. Clarified graphic requirements.
  16. Replaced Communication Riser Diagram with Communication Riser Spreadsheet.
  17. Added requirement for audit and alarm logs.
  18. Removed requirement for 1% factory training credits.
  19. Added/modified Figures 2 and 3 at end of specifications.
Section 23 00 10Jul 19, 2012 02:31 PM
 Replaced subsection .03 with new text, taking out the old table.

Section was updated primarily for the following reasons:

  1. To refer Design Professionals to current standards and guidelines and to delete old table to avoid providing duplicated, obsolete, or conflicting direction.
Section 23 31 00Jul 10, 2012 03:22 PM
 Modified heading of Part .01 and replaced text under subpart A

Section was updated primarily for the following reasons:

  1. To add miscellaneous general design requirements.
  2. To clarify requirement to define specific duct pressure classifications in each associated section of ductwork throughout the system to assure proper construction and reinforcement.
  3. To add recommendations for using round duct as much as possible.
  4. To add requirements for Seal level A per ASHRAE 189.1 and associated duct leak testing.
  5. To add requirements for low pressure drop systems with respect to achieving fan power limitation in ASHRAE 189.1.  
Section 26 29 23Jul 09, 2012 04:30 PM
 Insert Document Table with new text and update the associated word document "OPP VFD Guidespec"

Section was updated primarily for the following reasons:

    1. Revise OPP VFD Guidespec with respect to:
      1. Enclosure type requirements (Clarify Designer Notes for Type 1 vs. 12)
Division 26Jun 22, 2012 05:23 PM
 Modified various sections in Division 26

Section was updated primarily for the following reasons:

    1. Update BAS interconnection with electrical systems.
    2. Update testing requirements.
    3. Update elevator connection requirements.
    4. Insert several miscellaneous updates to section.
Section 23 21 00May 17, 2012 08:54 AM
 Subsection .02 B - revised requirements on combination shut-off balance valves.

Section was updated primarily for the following reasons:

    1. To Revise requirements on combination shut-off/balance valves to achieve more variable adjustment and precise flow measurement and to be able to read setting directly off the handle position rather than needing to find which internal venturi was supplied in the ball/venturi type and then having to look up chart.
Section 31 30 00 (no linked file)May 16, 2012 03:34 PM
 Added specification to address expansive aggregate

Section was updated primarily for the following reasons:

  1. Specification was added to address expansive aggregate
Section 03 00 01May 16, 2012 10:24 AM
 Section was added to reference new "Sructural Backfill and Compaction" Specification.

Section was updated primarily for the following reasons:

  1. Section was added to reference new "Structural Backfill and Compaction" Specification in Division 31.
Section 32 01 00May 15, 2012 02:08 PM
 Section was revised to reflect changes to hiring of testing agencies

Section was updated primarily for the following reasons:

  1. Section was revised to reflect changes to hiring of testing agencies.
Section 23 72 00Apr 18, 2012 09:51 AM
 Section 23 73 00, part .02, items B and F were modified. Remainder of section is unchanged.

Section was updated primarily for the following reasons:

  1. Unit Casings:  Added requirement for maring lights.
  2. Coil Sections:  Added requirement for stainless steel coil casings and structural supports for coils subjected to condensation and rearranged papagraphs for more logical order.
Section 23 21 23 (no Linked file)Apr 09, 2012 01:51 PM
 Modify subsection .03.A.6 of Section 23 21 23. Remainder of section is unchanged.

Section was updated primarily for the following reasons:

To define more detailed requirements for rubber spherical type vibration isolator flexible pipe connectors.

    1. EPDM rated for 250 degrees in lieu of neoprene.
    2. Construction designed to prevent pull out of rubber at flange connection.
    3. Vibration/sound reduction performance requirements.
    4. Control rods/cables.
    5. Recommended manufacturer for basis of design
Section 25 00 00Apr 06, 2012 08:17 AM
 Replaced Building Automation Systems document.

Section was updated primarily for the following reasons:

1.  Remove outdated specification from Standards while it is being revised and updated.

2.  Indicate new acceptable vendor list.

Section 25 90 00Feb 28, 2012 03:31 PM
 Modify current section to replace linked document with updated document.

Section was updated primarily for the following reasons:

1) Correct the number of space type classifications from 4 to 5.

Section 01 05 05.01Feb 28, 2012 02:27 PM
 Modify current section to include requirements for card readers.

Section was updated primarily for the following reasons:

1) Incorporate card reader requirements on mechanical and electrical rooms.

Section 23 21 13Jan 30, 2012 11:05 AM
 Additions to section 23 21 13

Section was updated primarily for the following reasons:

  1. To achieve better continuous operating performance of closed systems by improving air and dirt removal method.
  2. To keep system pressure drop low with full system flow dirt separation.
  3. To allow blowdown through recirculating bag filer assembly to avoiding need for ongoing makeup water and associated addition of dissolved air and losses of chemical treatment and anti-freeze solutions when present.
  4. To add schematic piping detail for closed hydronic plants.
Section 12 40 00Jan 26, 2012 12:37 PM
 Addition of section 12 40 00

Section was updated primarily for the following reasons:

  1. Add recycling and compost bin requirements to the published Design & Construction Standards.
Section 28 00 00Jan 16, 2012 11:32 AM
 Post Revised specifications from ACES

Section was updated primarily for the following reasons:

  1. To revise the specifications to conform to current system requirements.
Section 33 50 00Jan 12, 2012 10:02 AM
 Update 335000.01 to include 49 CFR Part 192 regulatory requirements for all PSU properties

Section was updated primarily for the following reasons:

  1. Add regulatory requirements of 49 CFR 191 and 192 to standards.
  2. Update campus system requirements.
Section 23 57 00Jan 09, 2012 10:45 AM
 Replace current section in its entirety to follow common industry practice and to expand section into three parts.

Section was updated primarily for the following reasons:

 1)      To follow common industry practice to apply shell and tube heat exchangers on steam to hot water applications in lieu of gasketed plate and frame.

2)      To expand section into three parts for more comprehensive General, Product and Installation requirements.

Section 23 05 01.02Jan 06, 2012 08:40 AM
 Click here to expand...

Section was updated primarily for the following reasons:

  1. To replace and improve requirements for shut off valves, which were previously deleted by accident.
  2. To add other general valve requirements.
Section 23 05 01_02 and 23 21 13Nov 03, 2011 09:15 AM
 Modify Secion 23 05 01_02 and Section 23 21 13_03 to delete conflicts and add cross references to other updated sections related to balancing valves in general and at pumps.

Section was updated primarily for the following reasons:

1)      To delete conflicts and add cross references to other updated sections related to balancing valves in general and at pumps.

Section 28 00 00Nov 02, 2011 11:32 AM
 Remove old uploaded document and replace with new version. Add 3 additional uploaded document.

Section was updated primarily for the following reasons:

  1. To incorporate new system and technology requirements.
Section 23 05 01Nov 01, 2011 02:44 PM
 Replace obsolete Mechanical Color Code painting 1. Follow current industry ANSI/ASME A13.1 Standard for color coding scheme and piping system identification. Comply with standard for lettering size, color scheme based on classification of contents, length of color field, locations and intervals, and visibility. http://www.bradyid.com/downloads/SMD_296.pdf?msgkey=downloadsDetail.pleaseWait.msg Also move mechancial room general painting requirements to Div 9. Also edit similarly if referenced in Div 21 and 22.

Section was updated primarily for the following reasons:

  1. To update mechanical systems color code identification labels per current industry standards.
  2. To coordinate cross references among disciplines.
Section 23 70 00Nov 01, 2011 01:05 PM
 Energy Recovery and Air Handling Units.

Section was updated primarily for the following reasons:

  1. Multiple and extensive additions, revisions and overall reorganization into General design intent and selection criteria, Product specifications, and Execution parts.
  2. To create new and separate subsections for Energy Recover Equipment and Air Handling Units.
Section 23 21 00.02Sep 26, 2011 09:04 AM
 Addition of section 23 21 00.02, Flow Balance and Differential Pressure Control

Section was updated primarily for the following reasons:

  1. To provide guidelines for application of manual isolation/balance valves and differential pressure regulating valves and proper primary/secondary flow balance for improved hydronic system operation and control.
Section 23 21 23Sep 21, 2011 11:05 AM
 Modify subsection .03, a.5 in Section 23 21 23. Remainder of section is unchanged.

Section was updated primarily for the following reasons:

1)    To delete reference to orifice plate due to relatively inefficiency (higher pressure loss) vs. venturi flow meter.

Revision 01 01 02Sep 21, 2011 10:27 AM
 Update requirements document to match current University expectations for Design Review Deliverables.

Section was updated primarily for the following reasons:

  1. Update requirements document to match current University expectations for Design Review Deliverables.
Section 09 90 00Sep 16, 2011 07:52 AM
 Update paint manufacturers.

Section was updated primarily for the following reasons:

  1. Coordination with current University paint contracts
Section 25 90 00Aug 15, 2011 01:40 PM
 Update to 25 90 00 EUMS Document rev3

Update to 25 90 00 EUMS Document rev3

Section 23 21 13Aug 15, 2011 11:32 AM
 Revision to 23 21 13.03 A, Hydronic Specialties

Section was updated primarily for the following reasons:

  1. To define more complete strainer requirements, including specific screen size requirements for various services and pipe sizes.
Section 23 22 00Jul 22, 2011 08:10 AM
 Revisions to Section 23 22 00 completed 7/22/2011

Section was updated primarily for the following reasons:

 1)    To define more complete strainer requirements, including specific screen size requirements for various services and pipe sizes.

Section 01 01 00 and 23 05 01Jul 22, 2011 08:09 AM
 Modify Sections 01 01 00 subsection .01 and 23 05 01 subsection .05 per the following (deletions are shown struck through and additions are double underlined). Remainders of sections are unchanged.

Sections were updated primarily for the following reasons:

 

1)      To relocate the Acronym List to a more General location Div1, since it covers equipment from many Divisions.

2)      The list was reorganized first with respect to the associated Specification/Standard Section number and then alphabetically within those sections.   

3)      To more closely follow common equipment acronyms generally accepted and used in the industry such as:

a.       ASHRAE 2009 Fundamentals

b.      US National CAD Standards.

4)      To reduce common coordination problems arising during design development and shop drawings review causing frustration among design consultants, PSU staff and contractors.  Examples include:

a.       “AHU” for Air Handling Unit in lieu of prior “ACF” (Air Conditioning Fan).  A Fan is a single component of a larger Air Handling Unit assembly with many components that performs the function of conditioning air.  Also, it is common to associate “Air Conditioning” unit with packaged DX unitary equipment and “Air Handling” unit with hydronic sources of heating and cooling.

b.      “MAU” for Makeup Air Unit in lieu of prior  “SFN” (Supply FaN) for the function of 100% outside air for makeup supply.  Again, technically a Supply Fan is a single component of a larger Unit assembly with many components that performs the overall function.  In larger units, one might have multiple, parallel “supply fans” in any sort of AHU or MAU or RTU, etc.  Using MAU to designate that function helps avoid confusion with limited function of a supply fan as a component.

5)      In general suffixes can be added to give acronyms some additional flexibility to allow more detailed descriptions of specific type or use for purposes of scheduling, specification grouping and for control tag purposes. 

6)      Individual equipment numbering:  The goal is to give each piece of equipment its own ID tag by type/subtype category and then either sequentially within each category (for primary equipment) or by room location of control sensor it serves (for terminal equipment).  Each subtype of HVAC pump is sequentially numbered within its fluid service type.  In other words, chilled water pumps are to be numbered sequentially within that category separate from hot water pumps and condenser water pumps, etc.   

7)      Design Professional must coordinate ID and equipment numbering scheme with OPP staff to improve and maintain consistency.

Section 25 00 00Apr 26, 2011 09:42 AM
 Criteria for Belimo PICCV valve selection developed by Steve Oskin

Section was updated primarily for the following reasons:

  1. To achieve uniform selection and installations if using pressure independent control valves.
Section 33 62 00Apr 25, 2011 11:20 AM
 Uploading new documents to the section, and fixing one misspelling.

Section was updated primarily for the following reasons:

  1. Update service entrance details to eliminate redundant strainers, add notes to Design Professional, and cross reference with other details.
  2. Correct pen colors in Acrobat documents.
  3. Revise sequences of operation.
  4. Correct a misspelling.
Section 07 00 00Apr 25, 2011 09:20 AM
 Additions to current section to include cross references.

Section was updated primarily for the following reasons:

 

1)     Add cross references to Div 1 for Performance Requirements of thermal insulation.

2)     Add cross reference to Div 33 Storm Drainage Utilities for coordination of green roof requirements.

Section 22 11 00Apr 22, 2011 01:45 PM
 Add more detailed general, materials, and installations requirements for pressed joint system.

Section was updated primarily for the following reasons:

1)    To add more detailed general, materials, and installation requirements.

2)    To remove proprietary references of pressed joint system.

3)    To prohibit copper push-on joint fittings.

Section 23 82 00 / 23 82 19Mar 08, 2011 01:38 PM
 Add new section to replace outdated references in 23 82 00 .04

Section was updated primarily for the following reasons:

  1. To expand this section into a 3 part format to more fully define requirements.
    1. Part 01: To list General Owner Requirements of design intent, selection criteria, quality assurance, submittals.  Crucial issues include:
      1. Integrated system design must account for adequate dehumidification.
      2. Ensuring acceptable Sound and Vibration levels.
    2. Part 02: To list the Product Requirements for manufactured equipment.
      1. Energy Efficient ECM fan motors with auto variable speed controls
      2. Thermal Insulation performance meeting High Performance Building Standard for IAQ and energy efficiency
      3. Filters (MERV 6-8)
      4. Accessories
      5. BAS Controls coordination
    3. Part 03: To list the Execution (Installation, Connections, and Start-up/functional performance testing) requirements.
Section 25 00 00Mar 07, 2011 12:59 PM
 Update Building Audtomation Systems (BAS) Guide Spec

Section was updated primarily for the following reasons:

  1. Changed the Spec Section # from 15900 to 25 55 00
  2. Added various equipment specifications and performance requirements for systems.
  3. Removed any and all Sequences of Operation from Part 4 of this BAS Guide Spec.
Section 23 64 00Dec 20, 2010 11:29 AM
 Click here to expand...

Section was updated primarily for the following reasons:

  1. To expand this section into a 3 part format to more fully define requirements.
    1. Part 01: To list General Owner Requirements of design intent, selection criteria, quality assurance, submittals, and warranties. Crucial issues include:
      1. Ensuring adequate turndown and piping system thermal mass for stable chiller operation in all operating conditions.
      2. Selecting equipment, designing piping arrangements and controls for optimizing energy efficiency.
      3. Use of free cooling options whenever practical
      4. Ensuring acceptable Sound and Vibration levels
      5. Refrigerant safety provisions
      6. Equipment service access and replacement provisions
      7. Ensuring systems have flow switches for chiller protection
    2. Part 02:  To list the Product Requirements for manufactured equipment.
      1. Refrigerant selection criteria
      2. Thermal Insulation performance meeting High Performance Building Standard for cooling systems.
      3. Electrical Power
      4. Controls with BAS interface
      5. Accessories
    3. Part 03:  To list the Execution (Installation, Connections, and Start-up/Commissioning) requirements.
      1. Factory start up
      2. Vibration Testing by OPP approved Vibration Analyst at startup.
Section 33 60 00, 33 61 00 and 33 62 00 (no files linked)Dec 20, 2010 10:38 AM
 Update sections with added content and document clarification.

Section was updated primarily for the following reasons:

  1. Clarify the intent of the design standard section.
  2. Clarify the intent and description of each standard detail and/or document.
Section 25 90 00Dec 03, 2010 12:00 AM
 Revise AHU Sequence of Operation and add supporting diagrams.

Section was updated primarily for the following reasons:

  1. Upgrades to technical sequences, point list, and schematic drawings for improved operations, energy savings and monitoring/alarming.
    1. Fan Tracking control.
    2. Requires independent outside air, return air and relief damper actuation.
  2. Added general clarifications and notes to design/construction teams.
  3. Corrections of typographical errors.

The changes between Rev 3 and Rev 4 are so extensive that the document is being replaced in its entirety rather than showing individual revisions throughout the body of the text.  A "changes tracked" version, which has viewing modes that can be user selected, can be made available upon request.

F:\EVERYONE\Design and Construction Standards - PSU_OPP\_Revisions\_In Progress-By Division\Div 25 - Integrated Automation (BAS)\3 - Final Review\25 90 00 AHU VAV - Rev Instructions.docx

Section 26 29 23Dec 01, 2010 02:10 PM
 Revise guidance and description of VFD specification, update guide specification with new document.

Section was updated primarily for the following reasons:

  1. Comprehensive rewrite of all 3 parts of specification, which includes:
  2. Part 1 General
    1. Added Summary, Definitions.
    2. Revised submittal requirements including single source responsibilities.
    3. Added quality assurance requirements including single source responsibilities.
  3. Part 2 Product Requirements
    1. Various technical clarifications and revisions.
    2. Added BAS Interface requirement for VFD.
    3. Improved description of criteria for selecting when bypass feature is required.
    4. Added optional features to be considered per application including control options and special enclosure requirements.
  4. Part 3 Execution
    1. Added installation requirements including special wiring and grounding requirements to achieve better installations and longer life from motors and drives.
    2. Detailed start up service requirements including adjustment of carrier frequency and confirmation of proper installation and grounding of each motor/drive application and coordination with BAS contractor.
    3. Added requirement for coordinated, detailed VFD schedules on drawings.
Section 23 00 01Nov 09, 2010 11:49 AM
 Coordinate with section 01 81 13, expand general HVAC design and coordination requirements, and general reorganization.

Section was updated primarily for the following reasons:

  1. Deleted "SUSTAINABILITY" requirements, which will be covered more comprehensively in 01 81 13 Sustainable Design Requirements.
  2. Expanded general HVAC design and coordination requirements.
  3. Reorganized existing text into body of new text where it applies.
Section 01 81 13Oct 28, 2010 02:55 PM
 Update to further describe sustainable design objectives, and to adopt ASHRAE Standard 189.1 as high performance "Green" Standard for the University.

Section was updated primarily for the following reasons:

  1. To further describe sustainable design objectives.
  2. To revise language to allow prescriptive option (for smaller, lower budget projects) for obtaining energy optimization target of 30% better than ASHRAE 90.1.
  3. To adopt ASHRAE Standard 189.1 as High Performance "Green" Standard for the University.

 

Note the following from ASHRAE Journal, June 2010
http://www.ashrae.org/docLib/20100622_AJGuidetoStandard1891.pdf

Summary
The intent of the energy efficiency section is to significantly reduce the energy consumption of new buildings through reductions in energy losses through the
building envelope, increased efficiencies in mechanical systems, reduced lighting loads, and other energy saving measures. Standard 189.1 requires that buildings comply with Standard 90.1-2007 and then, in general, adds more stringent requirements. Standard 189.1 requires that either on-site renewable energy is used as a prescriptive option, that renewable energy certificates are purchased (only allowed in some cases), or that the building complies with the performance option and uses additional energy-saving measures to make up the deficiency from not using on-site renewable energy.
 -- Page S28

 
Conclusions
Based on an initial analysis, Standard 189.1 yields significant energy savings over previous standards. In a weighted average, savings are approximately 30% relative to Standard 90.1-2007, with roughly one-third of those savings attributable to renewable energy and two-thirds attributable to energy efficiency.
-- Page S32

Section 25 90 00Oct 11, 2010 10:42 AM
 Upload new guide Sequence of Operations for Enterprise Utility Management System (EUMS) Equipment Control Strategies

Section was updated primarily for the following reasons:

  1. Added 'Emergency Demand Levels, Equipment Guidelines' for heat Pumps.
Section 22 40 00Oct 11, 2010 10:30 AM
 update requirements for water closets, urinals, and floor drains.

Section was updated primarily for the following reasons:

  1. Add dual flush requirements at some water closets.
  2. Require the use of waterless urinals at some locations.
Section 01 56 10Aug 16, 2010 11:00 AM
 Add outdoor air intake protection requirements

Section was updated primarily for the following reasons:

  1. Requirements were omitted when converting and relocating from older format in Div. 15 to new format in Div. 1.
Section 25 90 00Jun 22, 2010 02:54 PM
 Replace June 2009 version of the following embedded document: Remainder of section is unchanged.

Section was updated primarily for hte following reasons:

  1. Added 'Classroom Semester Break' portion of the sequence.
  2. Clarify the difference between air handlers serving critical critical spaces and air handlers serving non-critical spaces.
  3. Added verbiage to include both heating and colling setpoints in the emergency responses.
  4. Correct numerous grammatical and formatting mistakes.
Section 01 25 30 (no linked files)Apr 19, 2010 11:12 AM
 Revise Division 01 to provide a dedicated section (01 25 30) for safety requirements; add new fall protection requirements.

Section was updated primarily for the following reasons:

1) Provide new dedicated section for safety rquirements in facilities.

2) Add new fall protection requirements.

3) Clarify text in section 01 35 13.

Section 25 90 00Apr 19, 2010 10:55 AM
 Upload new guide Sequence of Operation for Air Terminal Units - Single Duct Variable Air Volume with Hot Water Reheat & Perimeter Heating

Section was updated primarily for the following reasons:

  1. Upgrades to technical sequences, point list, and schematic drawings for improved operation, energy savings, and monitoring/alarming.
  2. Added general clarifications and notes to design-construction teams.
  3. Corrections of typographical errors.
Sections 26 05 53 through 26 56 00Mar 18, 2010 10:00 AM
 Update of several sections within Division 26, including labeling, lift equipment requirements, lighting controls, generators, transfer switches, surge suppression, commissioning and emergency lighting.

Section was updated primarily for the following reasons:

  1. Clarify labeling of equipment and conductors.
  2. Revise the IEEE Standard 1584 reference.
  3. Revise requirements for lift equipment for draw-out breakers to allow for variations between suppliers and improve bidding.
  4. Update lighting control requirements.
  5. Update air quality permitting requirements of generators.
  6. Add transfer switch monitoring requirements to improve consistencey of equipment specifications and improve bidding.
  7. Add surge suppression at server room panelboards.
  8. Update commissioning requirements for electrical systems.
  9. Clarify emergency lighting requirements.
Sections 23 05 01 and 23 05 19Dec 04, 2009 08:57 AM
 Revise thermometer and gauge requirements in HVAC systems.

Removal of a paragraph in Section 23 05 01.

Section 23 05 19 was added primarily for the following reasons:

  1. To add requirements for pressure/temperature ports.
  2. Add General Owner Requirements in order to define basic design intent, selection criteria, quality assurance, submittals, and coordination for measuring instruments.
  3. To update the Product Requirements for the technical specification details of measuring instruments.
  4. To add Execution requirements to define typical installation requirements.
Revision 01 35 13Nov 10, 2009 11:11 AM
 Upload HMC Infection Control Policy at .02C

Section was updated in order to convey the Infection Control Policies at MSHMC.

Section 23 21 23Nov 02, 2009 11:21 AM
 Update requirements of flexible pump couplings for Base Mounted End Suction Pumps and Base Mounted Double Suction Pumps.

Section was updated primarily for the following reasons:

  1. To update the Equipment Requirements for the technical details of pump construction
    1. Goal - to define specific type of flexible couplings required and to disallow unacceptable type to achieve better flexibility performance and service life on couplings.
Section 01 05 05Oct 30, 2009 03:31 PM
 Update dumpster location requirements and compactor requirements.

Section was updated primarily to reflect fire code requriements.

Sections 08 00 01, 08 10 00, 08 50 00, 08 80 00Sep 21, 2009 02:38 PM
 Update to window and glazing standards.

Section was updated primarily for the following reasons:

  1. To develop and document General Owner Requirements in order to define basic design intent and selection criteria.
  2. To update the Product Requirements for the technical details of doors and windows in order to optimize window / glazing performance and achieve better, more serviceable windows and doors.
  3. Note the following special points:
    1. Coordination with Division 01 83 00, Facility Shell Performance Requirements for integrated design criteria of fenestration assemblies within building envelope to optimize energy and thermal comfort performance.
    2. Thermal performance requirements more stringent than Energy Code.
Section 01 35 13Aug 28, 2009 10:49 AM
 Upload new HMC Design Standards documents

Section was updated to indicate current requirements of the MSHMC.

 
Section 01 35 13Aug 28, 2009 10:47 AM
 Add new section 01 35 13

Section was updated primarily for the following reasons:

  1. To formally incorporate the unique requirements of the MSHMC into the body of the standards (instead of only appearing in the introduction).  Among other things, this will ensure future changes to these requirements are tracked, and will provide a place for future more detailed items.
  2. To provide a place for future inclusions of other unique facility requirements.
Section 28 00 00Aug 28, 2009 09:46 AM
 Upload new specifications document to standards.

Section was updated primarily for the following reasons:

  1. To update equipment specifications to reflect current manufacturer offerings.
  2. To correct details associated with specified equipment.
Section 13 21 00Aug 18, 2009 10:15 AM
 Modify minimum face velocity and component requirements of hoods in radioisotope laboratories.

Section was updated primarily for the following reasons:

  1. To improve energy performance (reduce consumption) of radioisotope laboratories while maintaining safety.
  2. To eliminate the use of manometers containing mercury in new installations.
Section 23 70 00Aug 13, 2009 01:14 PM
 Update air handler requirements regarding efficiency, system reliability, redundancy, identification, fan arrangement considerations, proper mixing, bearings, dampers, and referencing the sequence of operations.

Section was updated primarily for the following reasons:

  1. To develop and document General Owner Requirements in order to define basic design intent and selection criteria.
    1. Goal – to provide guidelines to promote and achieve Efficiency and Reliability
    2. Note the following special points:
      1. Select units with reduced maximum face velocity to minimize internal component pressure drops.
      2. Coordinate with Space Planning requirements.  Preference for central air handling equipment to be located indoors.
      3. Identification.
      4. Scheduling minimum fan efficiencies.
      5. Special bearing requirements.
      6. Evaluate blow-through vs. draw thru fan configurations for optimal overall net efficiency.
      7. Performance requirements for proper mixing.
  2. To update the Equipment Requirements for the technical details of central Air Handling Units.
    1. Goal – to improve specifications in order to achieve better performance and controls.
Section 25 90 00Jul 07, 2009 12:27 PM
 Updated temperature control sequence description and explanatory text

Reason for change:

  1. To explain the purpose and use of the guide temperature control sequences in section 25 90 00.
  2. To add a descriptive text for each sequence to aid the Professional in use and selection of each sequence.
Section 25 90 00Jul 07, 2009 12:24 PM
 Add a new document describing the sequences of operation necessary to accomplish the HVAC functions of the Enterprise Utility Management System (EUMS).

This document was added for the following reasons:

  1. To develop and document the integration of EUMS goals with the Building Automation System, including:
    1. Generate revenue by shifting electrical grid loads from high cost times to lower cost times.
    2. Minimize adverse effects on each utility's supply system caused by excessive load increases over short periods.
    3. Create a system that will enable quick load shedding on each utility in the event of a utility supply failure to minimize adverse effects in critical research areas.
  2. To develop and document the execution of this integration.
Section 23 21 23Jun 29, 2009 12:00 AM
 Replace current section in its entirety to include new requirements of general design and installation.

Section was updated primarily for the following reasons:

  1. To develop and document General Owner Requirements in order to define basic desgin intent and selection criteria.
    1. Goal - to provide guidelines to promote and achieve efficiency and reliability throughout entire operating range.
  2. To update the Equipment Requirements for the technical details of pump construction.
    1. Goal - to improve specifications in order to achieve better and more serviceable pumps.
  3. To develop and document the Execution (Installation, Operation, and Start-up/Commissioning) Requirements.
    1. Goal - to achieve better installations, better operating efficiency and longer life out of pump systems.
    2. Note the following special points:
      1. Manual balancing valves and Triple Duty Valves are not to be used at pump discharges.
      2. Pump leveling and base grouting requirements.
      3. Vibration Control and Final Alignment Requiprements.
      4. Impeller trimming requirements more stringent than ASHRAE 90.1.
Section 01 81 13None
 Added new subsection .04 in its entirety. Remainder of section unchanged.

Section was added primarily for the following reasons:

  1. To define supplemental Owner Requirements intended to achieve high performance of building envelope and integration with HVAC and lighting systems.
  2. To define the Design, Submission, Commissioning and Quality Control requirements pertaining to the building envelope to assure high quality, high performance of those components and assemblies.
  3. Note the following special points:
    1. Envelope component must be equal to or better than performance prescribed by the combination of High-Performance Building Design Standards cited in Part 2 of this section.
    2. Avoid sources of local thermal discomfort.
    3. Limitations of exterior glazed areas.
    4. Submission and approval requirements of Building Envelope Compliance Report that summarized the key performance characteristics of the envelope assemblies.
    5. Building Envelope commissioning and field quality control.