33 62 00 CAMPUS CHILLED WATER DISTRIBUTION

  1. General
    1. Much of University Park Campus is, or will be, served by a campus look chilled water system.  The chilled water system of each new building must be designed so as to be compatible with the characteristics of the campus chilled water system.
    2. Coordinating building connection requirements and proposed loads with Engineering Services, Office of Physical Plant.
  2. Details: Refer to miscellaneous typical guideline details below.  Adapt to project specific requirements.
DocumentVersion DateDescription
SK1 (AutoCAD file)  (PDF Document)      February 2012Campus chilled water system service entrance detail for buildings that do NOT require a heat exchanger.
Sequence of Operation August 2012Sequence of Operation for campus chilled water system service entrance detail for buildings that do NOT require a heat exchanger.
SK-2 (AutoCAD file)  (PDF Document)      March 2012Campus chilled water system service entrance detail for buildings that require a heat exchanger.
Sequence of Operation August 2012Sequence of Operation for campus chilled water system service entrance detail for buildings that require a heat exchanger.

Isolation Valve (AutoCAD file)

   (PDF Document)

 
Details of a campus chilled water isolation valve installation.

Air Vent (AutoCAD file)

   (PDF Document)    

 Detail of a campus chilled water air vent.

Sediment Blowoff (AutoCAD file

    (PDF Document)

 Detail of a campus chilled water sediment blowoff.
 Building Wall Penetration (AutoCAD file) 
    (PDF Document) 
 Detail of a campus chilled water building penetration.

 